Brighton Avenue Sewer Separation Project

PROJECT UPDATES
WE 4/9/21 Project Update 
  1. PWD cut In Valves installed in Rowe Avenue and Dorset Street in preparation for the temporary water system. 
  2. Erosion and sediment control devices installed within the project area. 
  3. Tree clearing at the end of Meriline completed for storm drain outfall work. 
  4. Rip Rap energy dissipation pad installed at the location 42" storm drain outfall 
  5. 20 LF of 42" storm drain outfall pipe installed at the end of Meriline.
Upcoming Work WE 4/16/21
  1. PWD cut in valves to be installed in Warwick Street and Lomond street.
  2. 42" storm drain work continues in Meriline Avenue working towards Rowe Avenue.
Stone Construction Entrance Installed to Prevent Erosion
Installation of 42 Inch Storm Drain Outfall Pipe Meriline
42 Inch Storm Drain Outfall Pipe Installation Complete
Installation of Riprap Energy Scour Pad


"This project was successfully bid in December of 2020 and awarded to DDI Construction at a contract price of $1,286,897.00.  
It is anticipated that the contractor will mobilize to the site the week of March 29th and begin construction work on Meriline Avenue the week of April 5th."

WE 4/2/21 Project Update:

DDI construction began to mobilize and bring materials and equipment to the site.

The first project weekly field meeting was held on site.

Utility test pits were completed on Lomond Street.

Upcoming Project Work WE 4/9/21:

The contractor will begin to install PWD water main cut in valves in Rowe Avenue (4/5/21) and Dorset Street (4/7/21) in preparation of setting up the project's temporary water system. The temporary water system is required to be able to replace the existing water mains in the project area.

The contractor will also begin to install a riprap scour protection pad in preparation for the installation of the 42" storm drain outfall pipe at the end of Meriline Avenue.


Facts Sheet update
Project Location Map update